FUL/353405/24 decided refuse Last updated 28/07/2025, 16:16

Application to install and operate a 30 MW Battery Energy Storage System (BESS) with access and related infrastructure.

Full Application

Medlock Road, Failsworth, Manchester, M35

M35

Full Proposal

Installation and operation of a 30 MW Battery Energy Storage System (BESS), including access and associated infrastructure.

Application Timeline

Application Registered
10/09/2024
Application Validated
08/10/2024
Target Decision Date
03/12/2024
Committee Date
23/04/2025
Decision Made
28/04/2025
Decision Issued
28/04/2025

Case Officer

Applicant

Mr Connor McKinley

Agent

Miss Chloe Jonczyk

6, De Salis Court, Droitwich, WR9 0QE

RCA Regeneration

More Information