FUL/353405/24 decided refuse
Last updated 28/07/2025, 16:16
Application to install and operate a 30 MW Battery Energy Storage System (BESS) with access and related infrastructure.
Full Application
Medlock Road, Failsworth, Manchester, M35
M35Full Proposal
Installation and operation of a 30 MW Battery Energy Storage System (BESS), including access and associated infrastructure.
Application Timeline
- Application Registered
- 10/09/2024
- Application Validated
- 08/10/2024
- Target Decision Date
- 03/12/2024
- Committee Date
- 23/04/2025
- Decision Made
- 28/04/2025
- Decision Issued
- 28/04/2025
Case Officer
Applicant
Mr Connor McKinley